|
INSIDE
THIS ISSUE |

|
|
|
| |
| |
|
OEB
Releases Enbridge Gas
Distribution 2005 Rate Decision
by
David
Brown
On November 1, 2004 the
Ontario Energy Board released its final decision on the
application by Enbridge Gas Distribution Inc. (EGD) for
2005 rates (RP-2003-0203). Although most issues raised by
the application were settled without a hearing, the OEB
was required to decide several issues of note.
Since the fall of 2002 EGD
had been bundling the natural gas commodity together with
utility assets to create transactional services such as
peak storage, loans and exchanges. The OEB decided that it
would be contrary to efforts to create competitive markets
for natural gas to allow EGD to bundle commodity gas with
utility assets and the Board directed EGD to refrain from
such activities by January 1, 2005. The Board signalled
its interest in EGD promoting an open market for surplus
transportation and storage assets, and asked EGD to
develop a methodology for making such surplus assets known
and available to unrelated market participants on a
non-discriminatory basis as soon as possible.
A second issue involved a
new storage contract EGD negotiated with Union for 19.9
bcf of storage for the period 2004 to 2014. EGD’s prior
storage contract with Union had used cost-based storage
rates; the new one used market-based rates that exceeded
the cost-based ones. Earlier this year Union obtained OEB
approval for the parties to, period of and space that was
subject to the new contract. In its rates case EGD sought
Board approval for the cost consequences of the new
contract. The Board declined to give its approval. Citing
concerns over the lack of solid evidence about ratepayer
benefits under the new contract and the lack of detail and
transparency in the RFP process that underpinned the
negotiated Union price, the Board denied EGD’s request
for recovery of the cost consequences of the contract. As
a result, the existing cost-based storage rates will
continue until 2006, at which time EGD and Union must
negotiate new market rates.
The Board’s decision also
brought to an end the long saga surrounding the deferred
tax issue relating to EGD’s transfer of its water heater
rental business to an affiliate in 1999 and the eventual
sale of that business to Centrica plc in 2002. The Board
allowed EGD to recover, in equal instalments over three
years, $23.9 million for the deferred taxes that became
payable between 1999 and 2002.
Finally, the OEB approved a
number of rate-making consequences flowing from EGD’s
decision to change its year-end from September 30 to
December 31 in 2005. Relying on last year’s Board
decision approving EGD’s unique request to use a
simplified CPI-adjusted methodology to set 2004 rates, EGD
proposed that the Board employ a similar methodology to
set rates during the stub period, October 1 to December
31, 2005. The Board refused to grant a rate increase for
the stub period, holding that EGD did not provide
sufficient evidence that costs would increase during the
stub period. |
|
|
|
Federal
Government Announces Quadrupling
of Wind Power Production Incentive (WPPI)
by
Aaron
Atcheson
With almost 95% of the
current $260 million WPPI budget allocated to wind energy
projects existing or in the process of construction or
final planning, the recent announcement that funding for
this popular program will be quadrupled was welcome news
to the wind energy industry. How WPPI will change as part
of this process was the subject of several sessions at the
2004 Canadian Wind Energy Conference in Montreal, October
17 – 20.
When the WPPI program was
first introduced, limited to qualifying projects
commissioned on or after April 1, 2002, the stated
goal was to encourage the development of a wind power
industry in Canada and to assist in the installation of
1000 MW of wind energy in Canada over five years, not to
mention contributing to meeting Canada’s goals under the
Kyoto Protocol. In order to ensure that smaller developers
and jurisdictions with less mature wind energy industries
not be excluded, caps were placed on the amount any
jurisdiction and any developer could receive. These
restrictions, which set limits of 300 MW of WPPI-supported
production per province/territory and $64 million total in
WPPI funds to any recipient, are now one of the main
subjects of debate as the program is expanded. With
Alberta now at 270 MW of installed capacity, the Canadian
Wind Energy Association and others are advocating the
raising or elimination of these caps.
The original WPPI program
also specified that WPPI funding could not be coupled with
other federal incentives. For example, electricity from
test wind turbines installed under the Canadian Renewable
and Conservation Expense (CRCE) provision of the federal Income
Tax Act is not eligible for WPPI funding. (CRCE allows
the cost of acquisition and installation of a test wind
turbine to be 100% deductible and such deductions can be
passed through to owners of flow-through shares.)
Similarly the greenhouse gas reduction credit trading
scheme being developed by Environment Canada will not
include power supported by WPPI. These restrictions are
currently being questioned by industry and advocacy
groups.
Finally, WPPI program
administrators are also looking for ways to support more
projects with the funding they have received. For example,
National Resources Canada (NRCan) is considering limiting
the WPPI funding to 30% of the nameplate capacity on any
project; although capacity factors on existing WPPI
recipient developments were commonly estimated at 40% by
developers, NRCan has found that most projects have
operated at around the 30% capacity factor level, meaning
that funds allocated to projects have not been paid out as
scheduled and opportunities to support additional wind
farms have been lost.
Overall, the industry is
encouraged by continued federal government support and is
looking forward to receiving the details of the next
version of the WPPI program. |
|
|
|
OEB
Clarifies "Special
Circumstances" for Transmission LTC Exemptions
by
Patrick
Duffy
Proponents of major
transmission line construction or expansion projects first
require leave from the Ontario Energy Board. Section 95 of
the OEB Act allows the Board to exempt any person
from the leave-to-construct requirements without a hearing
if in the Board’s opinion "special circumstances of
a particular case so require." In December 2003 the
OEB granted an exemption to Hydro One Networks for the
construction of its Parkway transmission line just north
of Toronto. Equating the phrase "special
circumstances" with circumstances that are
"unusual, uncommon or exceptional," the OEB
allowed Hydro One’s application, despite the utility’s
failure to file it in a timely manner, because the
exemption was necessary to avert rolling blackouts in the
Greater Toronto Area during the summer of 2005.
In a recent application by
Falconbridge Limited (RP-2004-0204/EB-2004-0412), the OEB
was again asked to grant an exemption from a formal leave
to construct hearing. Falconbridge proposed to construct a
new dedicated transmission line for one of its mines near
Sudbury. Falconbridge originally proposed to supply the
mine by means of a short tap from an idle transmission
line owned by INCO Limited, but abandoned the plan after
negotiations with INCO ended unsuccessfully. In its
application Falconbridge pleaded "special
circumstances" on the basis that it was unable to
reach an agreement with INCO in time to meet the mine’s
project development timelines, and therefore required an
exemption to be able to complete construction of the new
line in a timely fashion.
In its September 27, 2004
decision, the OEB accepted that "special
circumstances," in the sense used by the Board in the
Hydro One decision, might exist. Nonetheless, the Board
declined to exercise its discretion in favour of
Falconbridge. In the Board’s view, Falconbridge should
have been more prudent in its project planning by pursuing
alternative options for the supply of electricity at an
earlier stage. Nor was the Board satisfied that
Falconbridge had provided sufficient reasons for the
considerable delay in formulating an alternative supply
proposal and filing for leave to construct.
The Board did recognize
Falconbridge’s commercial need to proceed with the
proposed line on an expedited basis and without undue
delay. However, the Board ruled an exemption was not
necessary because it was willing to grant a
leave-to-construct order. The panel noted that this
approach preserved the ability of the Board to proceed on
the basis of its usual process without any adverse
consequences to Falconbridge. After satisfying itself that
the proposal was in the public interest, the Board granted
Falconbridge leave to construct.
The Falconbridge decision
signals that special circumstances alone may not be
sufficient to justify an exemption order. In addition to
demonstrating that the circumstances are "unusual,
uncommon or exceptional," a future applicant for an
exemption likely will need to show that it acted in a
timely manner and could not be accommodated under the
normal leave-to-construct process without suffering
adverse consequences. |
|
|
|
Register
Now for Seminar!
Hail
to the Chief!
The
Impact of the 2004 U.S. Presidential
Election on Canada-U.S. Energy Relations |
|
The Energy Group of Stikeman Elliott
LLP will be hosting a complimentary breakfast seminar
on "The Impact of the 2004 U.S. Presidential Election
on Canada-U.S. Energy Relations." The last session of
congress left comprehensive energy legislation on the
table. The panellists at this seminar will offer their
views of what the future will hold for U.S. energy policy
under the newly elected administration and whether the
next few years will see a different direction in U.S.–Canada
energy relations.
Topics
will include:
-
Opportunities
for Canadian companies to engage the new
administration and Congress on energy issues
-
The
chances of a comprehensive energy bill passing next
year, and what that will mean for Canadian companies
-
How
some high-profile energy issues – energy security,
supply, environment – will play out and what that
means for Canadian companies
-
Whether
clean air and climate change issues will assume
greater prominence next year
Guest
Speakers:
Bonnie
A. Suchman, Of Counsel, Troutman Sanders LLP
Ms.
Suchman is Of Counsel in the Washington, DC office and
practices energy law. She provides legislative and
strategic advice to the Canadian Electricity Association
regarding electricity policy issues and issues related to
U.S. energy bills. Ms. Suchman also provides advice to a
Canadian governmental agency regarding transmission
reliability issues and advice to a number of U.S.
investor-owned utilities.
Timothy
Egan, President, High Park Group; Senior Advisor, Canadian
Electricity Association
Mr.
Egan is president of the High Park Group, a public policy
consulting firm that focuses largely on energy issues out
of its offices in Toronto and Ottawa. He is retained by
the Canadian Electricity Association on a range of issues,
including U.S. advocacy (monitoring the U.S. Congress and
Administration on issues of interest to the Canadian
electricity industry).
Date
and Time:
Thursday,
December 2, 2004
7:30 a.m. – 9:00 a.m.
Location:
Stikeman
Elliott LLP – Toronto Office
53rd Floor, Commerce Court West, 199 Bay
Street, Toronto, Ontario
(southeast corner of King St. West and Bay St.)
To
register, or for more information, contact:
Shannon Gilleland by E-MAIL
or at (416) 814-7901. |
|
|
For
information regarding any of the above material, you are invited
to contact any member of our Energy Group: |
|